19- Architectural drawings, Central Power Plant
Appraisal, destruction and scheduling
Accruals
System of arrangement
Numbered
Conditions of access and use area
Conditions governing access
The collection is open for research use.
Conditions governing reproduction
Copyright restrictions may apply.
Language of material
Script of material
Language and script notes
Physical characteristics and technical requirements
Finding aids
MPE-1 Central Power Plant ,Renovations Campus Site Plan
MPE-2 Central Power Plant , Renovations System Schedule
MPE-4 Central Power Plant , Lower Floor Gas,Water, DWV Piping & Demolition Work
MPE-5 Central Power Plant , Upper Floor Mechanical & Plumbing Renovations
M-6 Central Power Plant , Lower Floor Steam Piping & Renovation Work
M-7 Central Power Plant , Lower Floor Condensate Piping & Demolition Work
M-8 Central Power Plant , Lower Floor HVAC Renovations
M-9 Central Power Plant , Upper Floor HVAC Renovations
M-10 Central Power Plant , Chiller And Pump Piping Isometric
M-11 Central Power Plant , Renovations Condensor Water pump And Piping isometric
M-12 Central Power Plant , Renovations Hot Water Boilers And Piping Isometric
R-1 Central Power Plant , Renovations Roof Plan
P-6 Central Power Plant Lower Floor Plumbing & Fire Protection Renovations
P-7 Central Power Plant , Upper Floor Plumbing & Fire Protection Renovations
E-4 Central Power Plant , Lower Floor Lighting & Power Demolition
E-5 Central Power Plant , Upper Floor Lighting & Power Demolition
E-6 Central Power Plant , Lower Floor Lighting Renovations
E-7 Central Power Plant , Lower Floor Power renovations
E-8 Central Power Plant , Upper Floor Lighting Power Renovations